Growth Deal Milestones Coming Up
NewsletterMilestones are anticipated in early 2020 for our Growth Deal projects.
The following milestones are anticipated in early 2020 for our Growth Deal projects:
- Gainsborough Growth Project Phase 1 – work to develop a new cinema will start in February 2020
- Gainsborough Growth Project Phase 2 – work will start on new homes being built on Bowling Green Lane in January 2020
- Skegness Gateway Project - construction work will run from January to September 2020 to open up a 31-ha greenfield site for mixed use commercial and leisure development
- Access to Employment Zones Phase 2, Grimsby - construction of a new, full-sized roundabout got under way in January 2020
- Agri-Food Centre of Excellence, Holbeach – works will commence on site in January 2020
- University Technology and Innovation Centre, Grantham – expected to open at the end of January 2020
- South Humber Infrastructure Investment Programme (SHIIP) Phase 2 South Humber Bank Link Road - scheme to complete by spring 2020
- A46-A15 Riseholme Roundabout, Lincoln – work will start on site in April 2020
- Advanced Engineering R&D Centre, University of Lincoln - works will start on site in March 2020
- Digital Technology Transport and Logistics Academy, Boston College - construction works will commence on site in February 2020
- Huttoft Boat Shed Visitor Centre - construction works will commence on site in January 2020
- Borderville Expansion Project, New College Stamford - construction works will start in February 2020